Use this activity to create work assignments by drawing on the Gantt. Simply select the area corresponding to the desired date, time, and Resource to create the work assignment. This action opens the New Activity assistant, and the Work Assignment option should be selected to create an assignment. Then you can select the Task and assign it to the preferred Resource as a direct allocation.
The Dispatch Console must be loaded with data, mainly Resources, and Work Tasks on the Work Task List and Gantt.
The unassigned or assigned task will be assigned to a resource as a direct allocation and it will be updated in the Gantt.