Perform this activity to view Resource Shifts created for different resources in one place. It is possible to edit or delete existing shifts or breaks and add additional shifts or breaks as required.
Additionally, you can update resource information in bulk, for example, Scheduling Dataset, by selecting the ellipsis menu in the column headers while in edit mode.
Note: The Resource Shifts page displays available shifts for the next five weeks by default. To view all created shifts instead, disable the Five-Week Shift Plan toggle. To view shifts for a specific date/date range outside the upcoming five weeks, disable the Five-Week Shift Plan toggle and select the desired dates using the Shift Start/Shift End date pickers.
Resource Shifts must be generated. Only the resources with assigned shifts will appear on the Resource Shifts page.
Shift deviations are created for the edited shift ensuring that the deviation persists even if the resource schedule is re-generated.