About Time Zone Handling in Resource Management

Concept

As Resource Management is a generic component in IFS Cloud and it's Resource Activities can be created from various sources, a consistant appoach is required when transacting with time based fields. Therefore, any time stamped dates sent to, or received by, Resource Management will be done so in Server time only, and then, if required, displayed in the the local device Working Time. Presentation of datetime fields will be handled differently depending on the page being viewed and the user may see datetime fields visualized in the following ways:

The following sections should be considered as a non-exhaustitive list of pages relevant to time zone handling for a resource.

Resource

Every resource has a time zone. It can be set manually or it will be derived via the following time zone prioritized inheritance logic:

  1.  The time zone of the scheduling resource's location address.
  2. The time zone of the Service Organization time zone.
  3. The time zone of the Primary Site.
  4. Server time zone.

ResourceTimeZone

Resource Availability

Working Time Calendars and Shift Patterns are static objects that produce a pattern of working time based upon a defined range of account dates. When shifts are generated and displayed in Resource Availability they will be displayed in accordance with the times defined in the Calendar/Shift Pattern and display the shifts in the resource's local time zone (regardless of the resource's time zone).

For example, a default calendar showing a shift of 8am-5pm for a Resource in New York (EDT, UTC -4) will look the same as a resource working the same shift datetime in Sydney (AEST, UTC+10). It will be represented as 8-5pm. Tooltip and Card views are available to visualize the datetime in UTC and the local device's Working Time.

Resource Availability

Resource Activity Allocations & Resource Analysis

Resource Allocations are entered and saved in the resource's time zone.

Miscellaneous Resource Allocations

When creating a Miscellaeous Resource Allocation for single or multiple resource, the Allocation Start and Allocation End dates will be entered and saved in the resource's time zone.

MRA View

After saving the MRA, the date and time can be visualized in the users time Working Time by clicking on the time zone badge (if enabled in Account settings).

MRA View

Tooltips and Card view will visualize the datetime in the local device Working Time.

Resource Shift Gantt & Resource Shift Calendar

Shift and Break intervals are represented in the logged in users local device time on the Resource Shift Gantt. For example, a Shift Planner in Stockholm (CEST, UTC+2) generating shifts for the same 8-5 Calendar for resources in New York (EDT, UTC -4) and in Syndey (AEST, UTC+10) would see both shifts displayed relative to the local device Working Time, i.e., the resource in New York shift's start time would be displayed as 02:00, and the resource in Sydney's as 16:00. In other words, it will be 2am for the Shift Planner in Stockholm when the New York resource begins his/ her shift.

Resource Shift Gantt