This activity is used to disconnect a scope from a project activity. A request scope can only be disconnected if the work tasks do not have any cost lines or invoiceable sales lines.
To diconnect the project activity, in the Scope tab of the Request Details page, select a scope line, click Project Connection, and then click Disconnect from Activity.
As a result of this activity, the request scope will be disconnected from the project activity, and it will not appear as a connection on the Project Monitoring > Activity Monitoring - Project Connections page.