Cost or revenue spreading is typically performed on a budget/forecast line when the Estimated to Complete (ETC) cost, committed cost, and/or revenue needs to be allocated into specific time periods where they are most likely to occur. You can manually spread cost or revenue into accounting periods, as well as receive assistance in distributing the budgeted or forecasted amount using predefined spreading profiles.

It is only possible to spread the part of the ETC that is not connected to a resource forecast or a contract change order. Additionally, the committed cost can only be spread if its associated cost elements are enabled for spreading. To enable cost elements for committed cost spreading, go to the PCE Code Part tab on the Project Setup Parameters page.

When spreading with a profile, the following options are available;

The cost/revenue spread amounts can be viewed and modified in Forecast Spread Details.

Prerequisites

System Effects