Use this activity to calculate the change in cost and revenue values based on your Schedule of Work Change Order.
When it is necessary to perform Calculate Value, it will be indicated under Pending Actions. Once the Calculate Value is performed, it is possible to analyze the Previous Cost, Current Cost, and Change in Cost values per Cost/Revenue Element, Sub Project, and Activity combination in the Change Order Summary page.
If the Contract Change Order Change Capturing Level of the sales contract or sub contract connected to your SOW Change Order is defined as Cost or Revenue Element, the user will not be allowed to perform the Create/Update Contract Change Order command until the Calculate Value is performed.
The Change Order Summary command will be enabled.