Connect/Disconnect Contract Change Orders

Explanation

Use this activity to connect contract change order forecasts to a budget/forecast version. Contract change order forecasts can be connected in the Project Forecast page using the Manage Forecast Connection. Use the Connect toggle to connect/disconnect selected contract change order forecasts in the Contract Change Orders section. The Connect All/ Disconnect All action commands can be used to connect/ disconnect all the Contract Change Orders listed in the Manage Forecast Connection page.

Change Order Forecasts Connected to EAC Workbench

It is possible to connect/disconnect contract change order forecasts to an EAC Workbench. Contract change order forecasts can be connected in the EAC Workbench page using the Manage Change Order Connections.

If a change has been done in the contract change order forecast after it has been connected to a project budget/forecast or an EAC Workbench, you are able to update the project budget/forecast or the EAC Workbench with this new changed amount using the Update command in Project Forecast Connections.

Change Order Included in Budget

The flag Change Order Included in Budget in the Manage Forecast Connections dialogue shows if a Contract Change Order is connected to the budget linked to the forecast. When the EAC Workbench is set to In Progress, the CCOs with this set to Yes will be disconnected from the forecast automatically to avoid duplication of the CCO values.

Prerequisites

System Effects