Add To Baseline

Explanation

Perform this activity when additional scope is added to the project and needs to be included in the existing project baseline. Executing this function will create a new baseline revision. Only the activities under the selected node will receive new baseline values. This process focuses on managing changes to the project. The project as a whole must already have an established baseline before it is permitted to add activities to the baseline.

Prerequisites

System Effects

Each time you Add to Baseline: