About Cost, Hours and Revenue Reported to Activity

Costs, hours and revenue can be reported to an activity from a wide range of connected objects, e.g. Purchase Orders, Shop Orders, Work Tasks, Sales Contracts, Document Packages, Tasks, Resources etc. (Refer to the document "About Activity Connections" for a complete list of objects). As the connected objects are planned and executed, values of cost, hours and revenue are reported back to the activity.

The cost and revenue values will always be reported from the connected objects in base and transaction currency. If multi-currency and/or project currency have been enabled for Budgeting and Forecasting purposes for the project, then cost and revenue will also be reported in base currency using the fixed Budgeting and Forecasting rate and/or the project currency. The values are displayed in base currency on all pages where cost and revenue are available, while the other currencies are displayed only in the Project Connections page.

Note: This document explains how different objects report cost, hours or revenue to an activity, refer to the tables below for detailed information about each object. For information on how connected objects retrieve progress and earned value, refer to the "About Earned Value and Progress" documentation.

Cost/Hours

Connected objects can report cost and hours information to the activity. The type of information retrieved depends on the connected object. The information is reported using the project cost elements that are defined for the connected object. The cost/hours information can be viewed for each activity in the Cost and Hours tabs in the Activity Monitoring page. It is also possible to view cost/hours per sub project or for the whole project in the Sub Project Monitoring and Project Monitoring pages respectively. In the Activity Monitoring page it is possible to view detailed information about the connected objects.

The possible stages of cost/hours values are:

Revenue

Connected objects can report revenue information to the activity. The type of information retrieved depends on the connected object. The information is reported using the project revenue elements that are defined for the connected object. The revenue information can be viewed for each activity in the Revenue tab on the Activity Monitoring page. It is also possible to view revenue per sub project or for the whole project in the Sub Project Monitoring and Project Monitoring pages respectively. In the Activity Monitoring page it is possible to view detailed information about the connected objects

The possible stages of revenue values are:

Reporting

Planned Cost Driver

The Planned Cost Driver determines from where the Planned Cost and Planned Hours are retrieved. When the Planned Cost Driver for the activity is:

Baseline Cost and Hours

All objects that report planned cost or hours will also contribute to Baseline costs and hours when a baseline is set for the project. The Baseline values are copied from the Planned values.

The following tables show how the different objects report cost, hours or revenue information to the activity. Any object which reports any type of cost, hours and revenue to projects will report these values on a cost/revenue element.

Cost, Hours and Revenue Progression of Project Connected Objects

The following tables display the cost, hours and revenue progression for various project-connected objects as they move through different stages during the planning and execution of the project. Any object reporting these values to projects will do so on a cost/revenue element.

There are three tables to display the progression:

Cost and Hours Progression

Activity Estimates

Activity Estimates are presented here and not in the table.

Object Object
Details
Planned Planned Committed Committed Used Actual
Project Tasks Planned values are taken from the Planned Cost or Planned Hours field in Tasks tab.
Activity Resources Planned values are taken from the Planned Cost and Planned Hours fields in the Activity Resource Planning/Planning tab. The values are calculated based on the cost associated with the Resource and are updated when planned hours are entered        
Document Package   Planned values are taken from the Cost and Hours fields in the Document Package page.        
Change Order   Values are taken from the Planned Cost and Planned Hours fields in Change Order Actions page.        
Design Object Planned values are taken from the Total Planned Cost and Total Planned Hours fields on the Design Object Project Connections page.  
Project Misc. Demand Supply Option: Purchasing

For a Purchase Part/No Part/Inventory Part requirement line, the planned cost is taken from the Planned Cost field in Planned Cost/Hours per Cost Element assistant (Cost Elements option from the command menu) and summed up to the Total Planned Cost field.
Planned Cost is retrieved in the following order:

  1. Expected Supplier Price per Unit
  2. Costing
  3. Inventory Value
  4. Estimated Cost

For a Purchase Part/Inventory Part requirement line, the planned hours are taken from the Planned Hours field in the Planned Cost/Hours per Cost Element assistant (Cost Elements option from the command menu) and summed up to the Hours Planned field. Hours of Purchase No Part requirement line will follow the same method as above and will not be summed up.

       
Supply Option:
Shop Order
The planned values are calculated based on part costing, depending on the posting control setup. Cost set 1 values should exist in part costing in order to get the project planned cost. Cost of the non-standard planned components are excluded from the planned cost. Non-Std. Planned items must be entered separately on the Miscellaneous Demand line for both cost and hours.

Planned hours are taken from the routing defined for the shop order in Shop Order Operations page.

       
Supply Option: PMRP / DOP The planned values are calculated based on part costing, depending on the posting control setup. Cost set 1 values should exist in part costing in order to get the project planned cost. These supply options use the full BOM (Bill of Material) costing for creating planned values.        
Direct Issue from Inventory When a miscellaneous demand for a part is entered.   When items are issued from standard inventory, or from project inventory (depending on the Material Allocation flag on the project). The cost is updated by the Inventory value. When the voucher created upon transfer of transaction has been updated in General Ledger.
Rental Charging

For a rental part requirement line, the planned cost is taken from the Planned Cost field in the Planned Cost/Hours per Cost Element assistant (Cost Elements option from the command menu) and summed up in the Total Planned Cost field. 

Planned cost is retrieved in the following order:

  1. Expected Supplier Price per Unit.
  2. Costing Inventory Value.
  3. Estimated Cost.

The expected supplier price per unit is only used as the planned cost and is not transferred to the purchase requisition. The order quotation functionality is not supported for miscellaneous rental parts.

When releasing the Purchase Requisition (PR) and creating the Purchase Order (PO), the Planned Committed Cost will transfer to the Purchase Order Line Part. When the PO is released.
When rental events and rental transactions have been generated.
When the voucher created upon transfer of transaction has been updated in General Ledger.
Forecast Demand  

Purchase Part:

For a Purchase Part/Inventory Part requirement line the cost is calculated the same way it is done for Misc. Demand/Misc. Part. Planned Cost is retrieved in the following order:

  1. Expected Supplier Price per Unit
  2. Costing
  3. Inventory Value
  4. Estimated Cost and is saved in the Activity Materials and Services page.

Manufacturing Part:

For a Manufactured Part the cost is calculated the same way it is done for Misc. Demand/Shop Order. If the structure contains other forecasted parts, these will not be included in the planned value. They will have to be entered separately. The values are saved in the Activity Materials and Services page.

       
Compatible Unit Execution Item Planning is done on the Execution Item in the Compatible Unit Navigator. The Compatible Unit must be released to report the planned cost to the activity.
Work is executed from the Work Order. If the Work Order planning originates from a Compatible Unit, the Report Planned Cost toggle is not enabled.

In the Compatible Unit Navigator/Work List/Resources tab, enter a line for a resource (Person or Tool/Equipment) with a defined cost rate. In the Compatible Unit Navigator/Work List/Materials tab, create a line for a Part and specify the quantity required. This applies to parts with the supply code Invent Order and Project Inventory.

For non-inventory purchase parts, in the Compatible Unit Navigator/Work List/No Part Requisition tab, create a line for a non-inventory Part/No Part and specify the units required.
       
Procurement Activity Planning is done on the Execution Item in the Compatible Unit Navigator. The Compatible Unit must be released to report the planned cost to the activity.
The procurement process that follows is done via PMRP. In the Compatible Unit Navigator/Work List/Materials tab, create a line for a Part and specify the quantity required. This applies to parts with the supply code Project Inventory.
       
Work Task   Work tasks are planned on a Work Order.

In the Work Task/Resources, enter a line and select the demand type: Persons, Crew or Tool/Equipment. Enter a resource group and/or a resource with a defined cost rate. The resource must be a Maintenance resource. The planned values will be held by the work task object.

In the Work Task/Material ta tab, create a material requisition line and specify the quantity required. The supplier price is the planned value, held by the purchase requisition object. For parts, the supply code can be Invent Order or Project Inventory:

  • For supply code: Inventory Order, the planned cost is taken as the Inventory value. The demand will be included in the MRP demand/supply calculation.
  • For supply code: Project Inventory, the supplier price is taken as the planned cost for the demand as it will be procured through the project. The demand will be included in the PMRP demand/supply calculation. The planned values will be held by the work task object.

To enter a purchase requisition, select the New Maintenance Purchase Requisition from the Purchasing command on the Work Task. Enter a line for a Part/No Part and specify the quantity required. The supplier price is taken as the planned value. The planned values will be held by the purchase requisition object.

In the Prepare Work Task/Planning tab, create a line for cost type External or Expenses and specify the quantity and cost required. The planned values are held by the work task object.
When a purchase requisition line is added for a Part/No Part, the planned committed cost is reported by the purchase requisition line object.

Note:
When a Purchase Order is created from the Purchase Requisition, the reporting of the planned committed cost is inherited by the purchase order line.
When the purchase order line is created for the Part/No Part and is in Planned status, the planned committed cost is reported by the purchase order line object.

When releasing the Work Task, the work task object reports committed cost and hours for:

  • Resources (Persons, Tool/Equipment)
  • External
  • Expenses
  • Material Requisition Lines with supply code Invent Order.
Report time on the operations in the Work Task/Time Reports tab.

When time is reported for a resource of type Person in the Work Task/Time Reports tab, the Used Cost is reported by the work task object.

When time is reported for a resource of type Tool/Equipment in the Work Task/Time Reports tab, the Used Cost is reported by the work task object.

When cost is reported for External and Expenses in the Work Task/Costs tab, the Used Cost is reported by the work task object.

When material with the supply code Invent Order is issued in the Work Task/Materials tab, the Used Cost is reported by the work task object.

When the Purchase Order Line for a Part/No Part has been received, the Used Cost is reported by the purchase order line object.

When the Purchase Order is matched with a Manual Supplier Invoice, the Used Cost is updated by the voucher created when the invoice is posted.


When time is reported for a resource of type Person in the Work Task/Time Reports tab. Used/Actual hours is reported by the work task object.

When hours is reported for a resource of type Tool/Equipment in the Work Task/Time Reports tab. Used/Actual hours is reported by the work task object.

Request Work Task  

Request work tasks are planned on a Request for service.

In the Request Work Task/Resources, enter a line and select the demand type: Persons, Crew, or Tool/Equipment. Enter a resource group and/or a resource that has a defined cost rate. The resource must be defined as a Service resource. The planned values will be held by the work task object.

In the Request Work Task/Material tab, create a requisition line for material, requisition or shipment and specify the quantity required. The supplier price is taken as the planned value. The planned values will be held by the purchase requisition object. The selected supply code determine how the demand is supplied:

  • For supply code: Inventory Order, the planned cost is taken as the Inventory value. The demand will be included in the MRP demand/supply calculation.
  • For supply code: Project Inventory, the supplier price is taken as the planned cost for the demand as it will be procured through the project. The demand will be included in the PMRP demand/supply calculation. The planned values will be held by the work task object.
  • For supply code: Purchase Order, enter a line for a Part/No Part and specify the quantity required. The supplier price is taken as the planned value. The planned values will be held by the purchase requisition object.
  • For supply code: Shipment Order, the planned cost is taken as the Inventory value.

In the Request Work Task/Planned Cost and Sales tab, create a line for either cost type External or Expenses and specify the quantity and cost required. The planned values are held by the work task object.

Planned committed cost is reported for the purchase flow.

When the purchase requisition line is added for a Part or No Part, the planned committed cost is reported by the purchase requisition line object.

Note:

When a Purchase Order is created from the Purchase Requisition, the reporting of planned committed cost is inherited by the purchase order line.

When the purchase order line is created for the Part and it is in Planned status, the planned committed cost is reported by the purchase order line object.

When the Request is released, the associated work task is also updated to released status. The work task object reports committed cost and hours for:

  • Resources (Persons, Tool/Equipment)
  • External
  • Expenses
  • Material Requisition Lines with supply code Invent Order.
  • When reserving Material for the material line with supply code: Shipment Order.

When time is reported on the Request Work Task/Time Reports tab for a resource of type Person, Crew or Tool/Equipment, the Used Cost is reported by the work task object.

When cost is reported for External and Expenses in the Request Work Task/Planned Cost and Sales tab, the Used Cost is reported by the work task object.

Material requisitions:
When material with the supply code Invent Order is issued in the Request Work Task/Materials tab, the Used Cost is reported by the work task object.

Purchase Orders Receiving Parts:
When the Purchase Order Line for a Part has been received, the Used Cost is reported by the purchase order line object.

Invoice Matching: When the Purchase Order is matched with a Manual Supplier Invoice, the Used Cost is updated by the voucher created when the invoice is posted.

When the Shipment Order is delivered.

Time is reported in the Request Work Task/Time Reports tab.

When time is reported for a resource of type Person, the Used/Actual hours are reported by the work task object.

When hours are reported for a resource of type Tool/Equipment in the, the Used/Actual hours are reported by the work task object.
Planning Item   The value is taken from the Project Deliverables Design /Cost/Hours tab.     When issuing standard planned items from Inventory.  
Customer Order Line Cost and hours are retrieved from the connected objects, depending on the supply option. Sales Overhead is retrieved from the sales overhead cost calculated for part in Part Cost. Updated by subsequent supply orders when they are released. Sales Overhead cost is retrieved from Part Cost. Updated by subsequent supply orders when they are further processed – refer to the relevant object type in this table.
Purchase Requisition Line Part / No Part   When a PR line is added for a Part/No Part/Rental Part and then released.      
Purchase Order Line Part/ No Part/ Rental Part   When a PO line is created for the Purchase Part/No Part/Rental Part and is in Planned status. When the order for a Purchase Part/No Part/Rental Part has been released. When the order for a Purchase Part/No Part has been received.

When rental events and rental transactions have been generated for the Rental Part.

When the voucher created upon transfer of transaction has been updated in General Ledger.
Purchase Order Change Order Part / No Part The delta (in value) between the current purchase order and the active change order (includes statuses Planned, Released, Authorized) for Part/No Part/Rental Part. When the voucher created upon transfer of transaction has been updated in General Ledger.
Shop Order Requisition   When a shop order requisition line is added for a part through Project Material Requirements Planning (PMRP) or Project Master Scheduling (Project MS)      
Shop Order     When the shop order is in Planned state.

Values are taken from the Planned Cost field in the Shop Orders Project Cost Analysis page.
When the Shop Order is released. Values related to operations are taken from the routing defined for the shop order (Shop Order Operation page)

When the Shop Order is released. Values related to material are taken from the Shop Order components and Shop Order Costing (Shop Order Costs page)

When the Shop Order is released. Values related to Subcontracting are taken from the Shop Order routing and Shop Order Costing.

When the Shop Order is released. Overhead values will be taken if General Overheads are defined in Part Cost tab.
Hours are updated when reporting time on the Shop Order.

Updated when reporting time and issuing material to the Shop Order.
When the voucher created upon transfer of transaction has been updated in General Ledger.
DOP Header       Reported from connected DOP orders (SO, PO) through the DOP Header. When hours are Reported from connected DOP orders supply (SO, PO) through the DOP header.

Reported from connected DOP order supply (SO, PO) when it is further processed through the DOP Header; refer to the relevant object type in this table.
Note! When Transactions have been transferred the used costs are displayed under the voucher rows connections instead of under the DOP header connection.
Reported from connected DOP orders supply (SO, PO) when it is further processed all the way to voucher creation upon transfer of related transactions updated in the General Ledger through the DOP header. Refer to the relevant object type in this table.

Note: When Update GL Vouchers has been run, the actual costs are displayed under the General Ledger Voucher Row connections.
Material Requisition Line   When the part is Reserved. For parts with Supply Code = Inventory Order. When the part is Issued. For parts with Supply Code = Inventory Order. When the voucher created upon transfer of transaction has been updated in General Ledger.
Project Transaction Time Reporting     When time is reported on an activity. When the transactions are confirmed and the value in the Create Cost Accounting field of the Report Code is either Yes or No, Update Project Cost. When the voucher created upon transfer of transaction has been updated in General Ledger.
Cost Reporting       When cost is registered in the Project Time and Cost Registration page. When the voucher created upon transfer of transaction has been updated in General Ledger.
Project Inventory Transfer         When the quantity has been transferred from one project inventory to the present project inventory; the original project inventory decreases in cost. When the voucher created upon transfer of transaction has been updated in General Ledger.
Sub Contract   Planned cost is reported before activating the revision when selecting the Report Planned Cost slider switch, and is updated when selecting the Update Planned Cost menu option. The planned cost is reported automatically when the revision is activated. Planned committed cost is reported when call off values are entered on the sub contract. Planned call off amount is equal to the planned committed cost. Committed cost is reported when the call off is released.    
Voucher Row         When voucher rows are created that report cost to a project activity. Examples:
 
  • When a manual voucher is created that reports cost to the project.
  • When vouchers are created for different transactions, they replace the Used value reported from the originating transactions, e.g. inventory transactions that become MPL vouchers.
  • When a supplier invoice is posted with a Project Id.
  • When receiving and certifying a sub contract valuation.
 
General Ledger Voucher Row           When vouchers rows that report cost to project activities have been updated to General Ledger.

 

Cost Progression for Customer Orders with Various Supply Options

Cost and hours will be as follows for different supply options in Customer orders.

Supply Code Planned Planned Committed Committed Used
Inventory Order Planned cost is retrieved in following hierarchy:

1. Cost set 1 values from IFS Costing.
2. Inventory value of the inventory part.
3. Estimated material cost of the inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported through the connected Customer Order line.
Updated when subsequent supply orders are released.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Project Inventory For manufacturing parts, cost is retrieved from part costing where as for purchased parts as in Purchase order Direct (inventory).

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
Updated when subsequent supply orders are released.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Purchase Order Direct (inventory) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.
2. From price list tab in supplier for purchase part page.
3. Price per part from supplier for purchase part.
4. Cost set 1 values from IFS Costing.
5. Inventory value of the inventory part.
6. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a Purchase Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purchase Order Direct 1 (inventory) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From price list tab in supplier for purchase part page.

3. Price per part from supplier for purchase part.

4. Cost set 1 values from IFS Costing.

5. Inventory value of the inventory part.

6. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a Purchase Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purchase Order Direct 2 Alt 3 (inventory) Planned cost is retrieved in following hierarchy:

1.Cost set 1 values from IFS Costing.

2. Inventory value of the inventory part.

3. Estimated material cost of inventory part.

If a Sales Over Head is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a Purchase Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Non-Inventory Planed cost is retrieved from Cost field in Non-Inventory Sales Part page

Cost is reported under Customer Order to the connected activity.
Updated when subsequent supply orders are released. Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Project No planned cost reported. No planned committed cost reported. No committed cost reported. No planned cost reported.
Purchase Order Direct (non-inv) Planned cost is retrieved in the following order of priority: >
1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till arrival transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purchase Order Direct 1 (non-inv) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From price list tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for the No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till arrival transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purchase Order Direct 2 Alt 2 (non-inv) Planned cost is retrieved in the following order of priority: >
1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till delivery transactions are transferred, used cost is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Shop Order Planed cost is retrieved from Cost set 1 values of IFS Costing.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When the shop order is in Planned state.

Values are taken from the Planned Cost field in the Shop Orders Project Cost Analysis page.
When the shop order is in released state. Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.

Used Cost incurred in shop order is reported as a typical shop order.
DOP Order Planed cost is retrieved from Cost set 1 values of IFS Costing.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
  When the DOP order is in released state. Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.

Used Cost incurred in DOP is reported as a typical DOP.
Purchase Order Transit (inventory) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

4. Cost set 1 values from IFS Costing.

5. Inventory value of the inventory part.

6. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planed cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a Purchase Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till arrival transactions are transferred.
After transferring, used cost is reported under respective voucher rows.
IntInt. Purch Order Trans 1 (inventory) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

4. Cost set 1 values from IFS Costing.

5. Inventory value of the inventory part.

6. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a Purchase Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till arrival transactions are transferred.

After transferring, used cost is reported under respective voucher rows.
Int. Purch Order Trans 2 Alt 3(inventory) Planned cost is retrieved in following hierarchy:
1. Cost set 1 values from IFS Costing.

2. Inventory value of the inventory part.

3. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
When order is created for the Purchase Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for the Purchase Part has been released.

Cost for the Purchase Order is reported under Pur Req/Pur Order to the connected activity.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
Till delivery transactions are transferred, used cost from Sales Overhead is reported under Customer Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till delivery transactions are transferred.

After transferring, used cost is reported under respective voucher rows.
Purchase Order Transit (non-inv) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From price list tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till arrival transactions are transferred, used cost is reported under Pur Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purch Order Trans 1 (non-inv) Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till arrival transactions are transferred, used cost is reported under Pur Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Int. Purch Order Trans 2 Alt 2
(non-inv)
Planned cost is retrieved in the following order of priority:

1. Price from Supplier agreement.

2. From Price List tab in Supplier for Purchase Part page.

3. Price per part from Supplier for Purchase Part page.

Cost is reported under Customer Order to the connected activity.
When order is created for the No Part and is in the Planned status.

Cost is reported under Pur Req / Pur Order to the connected activity.
When order for a No Part has been released.

Cost for the Purchase Order is reported under Pur Order to the connected activity.
Till arrival transactions are transferred, used cost is reported under Pur Order to the connected activity.

After transferring transactions, used cost is reported under respective voucher rows.
Not Decided (Inv) Planed cost is retrieved in following hierarchy:

1.Cost set 1 values from IFS Costing.

2. Inventory value of the inventory part.

3. Estimated material cost of inventory part.

If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost.

Cost is reported under Customer Order to the connected activity.
Updated when subsequent supply orders are released.

Cost for the Sales Overhead is reported under Customer Order to the connected activity.
N/A
Not Decided (Non-Inv) Planned cost is retrieved from Cost field in the Non-Inventory Sales Part page.

Cost is reported under Customer Order to the connected activity.

Updated when subsequent supply orders are released. N/A

Revenue Progression of Project Connected Objects

Updating of revenue on objects is performed against project revenue elements. Revenue objects do not report progress. The objects report revenue to the activity as follows:

Revenue Object Estimated Planned Preliminary Posted Actual
Activity Estimate Retrieved from the Estimated Revenue field in the Activity Scope and Schedule/Estimates tab.        
Sales Contract Project
(Sales Contract and Application for Payment)
  Retrieved from Sales Contract Line Items that have the Active revision status. The Report Planned Revenue slider switch can be used to view the previously planned revenue.      
Work Task   When the Work Order Line is transferred to a Customer Order Line.      
Request Work Task When the Request Line is transferred to a Customer Order Line.

Customer Order Line Revenue

  When a Customer Order Line or Customer Order Rental Line is connected to an activity.      
Customer Order Invoice Line     When a Customer Order Invoice is created.    
Invoicing Plan   When the Invoicing Plan Line is created with the Sales Amount.      
Project Transaction Revenue   When a Project Transaction is entered which can be invoiced and has a Sales Price.      
Invoice Posting Row

(Project Invoice)
(Instant Invoice)
(Customer Invoice)

    When the Project/Instant/Customer Invoice is saved.    
External Invoice Posting Row (External Customer Invoice)     When the External Customer Invoice is loaded.    
Voucher Row       When Hold table voucher rows are created that report revenue to project activities, for example:
  • When a manual voucher is created that reports revenue to the project.
  • When submitting and certifying a sales contract application for payment.
  • When the Customer Order Invoice is posted.
  • When the Project/Instant/Customer Invoice is posted.
  • When the External Customer Invoice is posted.
 
General Ledger Voucher Row         When Hold table vouchers rows that report revenue to project activities are updated to General Ledger.

A Step by step example on how important activity fields are used:

For this example we work on a project containing only one activity called "Specify and purchase engine for winch". In order to complete this activity some engineers have to do a detailed specification of which engine to buy, and later the purchase department is involved in the communication with the selected supplier. The planned cost driver for all of the objects is Connected Objects, except for the Activity Resources object, for which the planned cost driver is Activity Resources. The progress method is Connected objects.

Step 1

Project Cost Element Estimated Cost Estimated Hours
Material 100,000
Work 3,000

30

Sum 103,000

30

Step 2

Now we get the following results:

Project Cost Element Estimated Cost Planned
Cost
Estimated Hours Planned Hours
Material 100,000  
Work 3,000

3,200

 30

32
Sum 103,000

3,200

 30

32

Step 3

Now we get the following results:

Project Cost Element Estimated Cost Planned
Cost
Earned Value - Cost Scheduled Work - Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours
Material 100,000
Work 3,000

3,200

1,600

800

30

32

16

8

Sum 103,000

3,200

1,600

800

30

32 16               8

Step 4

Now we get the following results:

Project Cost Element Estimated Cost Planned Cost Earned Value -
Cost
Scheduled Work -
Cost
Committed Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours
Material 100,000 90,000 22,500 90,000
Work 3,000      3,200 3,200 800 30 32 32 8
Sum 103,000 93,200 3,200 23,300 90,000 30 32 32 8

Step 5

Now we get the following results:

Project Cost Element Estimated Cost Planned Cost Earned Value -
Cost
Scheduled Work -
Cost
Committed Cost Used Cost Actual Cost
Material 100,000 90,000 45,000 90,000
Work 3,000 3,200 3,200 1,600  900
Sum 103,000 93,200 3,200 46,600 90,000 900
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
Hours
Used/Actual Hours
Material
Work 30 32 32

16

10
Sum 30 32 32

16

10

Step 6

Now we get the following results:

Project Cost Element Estimated Cost Planned Cost Earned
Value -
Cost
Scheduled Work -
Cost
Committed Cost Used Cost Actual Cost
Material 100,000 90,000 45,000 90,000 45,000 45,000 22,500
Work 3,000 3,200 3,200 3,200 2,250 2,250
Sum 103,000 93,200 48,200 93,200 45,000 47,250 24,750
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
Hours
Committed Hours Used/Actual Hours
Material
Work 30 32 32 32 25
Sum 30 32 32 32 25