Costs, hours and revenue can be reported to an activity from a wide range of connected objects, e.g. Purchase Orders, Shop Orders, Work Tasks, Sales Contracts, Document Packages, Tasks, Resources etc. (Refer to the document "About Activity Connections" for a complete list of objects). As the connected objects are planned and executed, values of cost, hours and revenue are reported back to the activity.
The cost and revenue values will always be reported from the connected objects in base and transaction currency. If multi-currency and/or project currency have been enabled for Budgeting and Forecasting purposes for the project, then cost and revenue will also be reported in base currency using the fixed Budgeting and Forecasting rate and/or the project currency. The values are displayed in base currency on all pages where cost and revenue are available, while the other currencies are displayed only in the Project Connections page.
Note: This document explains how different objects report cost, hours or revenue to an activity, refer to the tables below for detailed information about each object. For information on how connected objects retrieve progress and earned value, refer to the "About Earned Value and Progress" documentation.
Connected objects can report cost and hours information to the activity. The type of information retrieved depends on the connected object. The information is reported using the project cost elements that are defined for the connected object. The cost/hours information can be viewed for each activity in the Cost and Hours tabs in the Activity Monitoring page. It is also possible to view cost/hours per sub project or for the whole project in the Sub Project Monitoring and Project Monitoring pages respectively. In the Activity Monitoring page it is possible to view detailed information about the connected objects.
The possible stages of cost/hours values are:
Connected objects can report revenue information to the activity. The type of information retrieved depends on the connected object. The information is reported using the project revenue elements that are defined for the connected object. The revenue information can be viewed for each activity in the Revenue tab on the Activity Monitoring page. It is also possible to view revenue per sub project or for the whole project in the Sub Project Monitoring and Project Monitoring pages respectively. In the Activity Monitoring page it is possible to view detailed information about the connected objects
The possible stages of revenue values are:
The Planned Cost Driver determines from where the Planned Cost and Planned Hours are retrieved. When the Planned Cost Driver for the activity is:
All objects that report planned cost or hours will also contribute to Baseline costs and hours when a baseline is set for the project. The Baseline values are copied from the Planned values.
The following tables show how the different objects report cost, hours or revenue information to the activity. Any object which reports any type of cost, hours and revenue to projects will report these values on a cost/revenue element.
The following tables display the cost, hours and revenue progression for various project-connected objects as they move through different stages during the planning and execution of the project. Any object reporting these values to projects will do so on a cost/revenue element.
There are three tables to display the progression:
Activity Estimates
Activity Estimates are presented here and not in the table.
Object | Object Details |
Planned | Planned Committed | Committed | Used | Actual |
Project Tasks | Planned values are taken from the Planned Cost or Planned Hours field in Tasks tab. | |||||
Activity Resources | Planned values are taken from the Planned Cost and Planned Hours fields in the Activity Resource Planning/Planning tab. The values are calculated based on the cost associated with the Resource and are updated when planned hours are entered | |||||
Document Package | Planned values are taken from the Cost and Hours fields in the Document Package page. | |||||
Change Order | Values are taken from the Planned Cost and Planned Hours fields in Change Order Actions page. | |||||
Design Object | Planned values are taken from the Total Planned Cost and Total Planned Hours fields on the Design Object Project Connections page. | |||||
Project Misc. Demand | Supply Option: Purchasing |
For a Purchase Part/No Part/Inventory Part requirement line, the
planned cost is taken from the Planned Cost field in
Planned Cost/Hours per Cost Element assistant (Cost
Elements option from the command menu) and summed up to the Total
Planned Cost field.
For a Purchase Part/Inventory Part requirement line, the planned hours are taken from the Planned Hours field in the Planned Cost/Hours per Cost Element assistant (Cost Elements option from the command menu) and summed up to the Hours Planned field. Hours of Purchase No Part requirement line will follow the same method as above and will not be summed up. |
||||
Supply Option:
Shop Order |
The planned values are calculated
based on part costing, depending on the posting control setup. Cost
set 1 values should exist in part costing in order to get the project
planned cost. Cost of the non-standard planned components are excluded
from the planned cost. Non-Std. Planned items must be entered separately
on the Miscellaneous Demand line for both cost and hours.
Planned hours are taken from the routing defined for the shop order in Shop Order Operations page. |
|||||
Supply Option: PMRP / DOP | The planned values are calculated based on part costing, depending on the posting control setup. Cost set 1 values should exist in part costing in order to get the project planned cost. These supply options use the full BOM (Bill of Material) costing for creating planned values. | |||||
Direct Issue from Inventory | When a miscellaneous demand for a part is entered. | When items are issued from standard inventory, or from project inventory (depending on the Material Allocation flag on the project). The cost is updated by the Inventory value. | When the voucher created upon transfer of transaction has been updated in General Ledger. | |||
Rental Charging |
For a rental part requirement line, the planned cost is taken from the Planned Cost field in the Planned Cost/Hours per Cost Element assistant (Cost Elements option from the command menu) and summed up in the Total Planned Cost field. Planned cost is retrieved in the following order:
The expected supplier price per unit is only used as the planned cost and is not transferred to the purchase requisition. The order quotation functionality is not supported for miscellaneous rental parts. |
When releasing the Purchase Requisition (PR) and creating the Purchase Order (PO), the Planned Committed Cost will transfer to the Purchase Order Line Part. | When the PO is released. | When rental events and rental transactions have been generated. |
When the voucher created upon transfer of transaction has been updated in General Ledger. | |
Forecast Demand |
Purchase Part:
Manufacturing Part: |
|||||
Compatible Unit | Execution Item | Planning is done on the Execution Item in the
Compatible Unit Navigator. The Compatible Unit must be released to report
the planned cost to the activity. Work is executed from the Work Order. If the Work Order planning originates from a Compatible Unit, the Report Planned Cost toggle is not enabled. In the Compatible Unit Navigator/Work List/Resources tab, enter a line for a resource (Person or Tool/Equipment) with a defined cost rate. In the Compatible Unit Navigator/Work List/Materials tab, create a line for a Part and specify the quantity required. This applies to parts with the supply code Invent Order and Project Inventory. For non-inventory purchase parts, in the Compatible Unit Navigator/Work List/No Part Requisition tab, create a line for a non-inventory Part/No Part and specify the units required. |
||||
Procurement Activity | Planning is done on the Execution Item in the
Compatible Unit Navigator. The Compatible Unit must be released to report
the planned cost to the activity. The procurement process that follows is done via PMRP. In the Compatible Unit Navigator/Work List/Materials tab, create a line for a Part and specify the quantity required. This applies to parts with the supply code Project Inventory. |
|||||
Work Task | Work tasks are planned on a Work
Order. In the Work Task/Resources, enter a line and select the demand type: Persons, Crew or Tool/Equipment. Enter a resource group and/or a resource with a defined cost rate. The resource must be a Maintenance resource. The planned values will be held by the work task object. In the Work Task/Material ta tab, create a material requisition line and specify the quantity required. The supplier price is the planned value, held by the purchase requisition object. For parts, the supply code can be Invent Order or Project Inventory:
To enter a purchase requisition, select the New Maintenance Purchase Requisition from the Purchasing command on the Work Task. Enter a line for a Part/No Part and specify the quantity required. The supplier price is taken as the planned value. The planned values will be held by the purchase requisition object. In the Prepare Work Task/Planning tab, create a line for cost type External or Expenses and specify the quantity and cost required. The planned values are held by the work task object. |
When a purchase requisition line
is added for a Part/No Part, the planned committed cost is reported
by the purchase requisition line object. Note: When a Purchase Order is created from the Purchase Requisition, the reporting of the planned committed cost is inherited by the purchase order line. When the purchase order line is created for the Part/No Part and is in Planned status, the planned committed cost is reported by the purchase order line object. |
When releasing the Work Task, the work task object reports committed cost and hours for:
|
Report time on the operations in
the Work Task/Time Reports tab. When time is reported for a resource of type Person in the Work Task/Time Reports tab, the Used Cost is reported by the work task object. When time is reported for a resource of type Tool/Equipment in the Work Task/Time Reports tab, the Used Cost is reported by the work task object. When cost is reported for External and Expenses in the Work Task/Costs tab, the Used Cost is reported by the work task object. When material with the supply code Invent Order is issued in the Work Task/Materials tab, the Used Cost is reported by the work task object. When the Purchase Order Line for a Part/No Part has been received, the Used Cost is reported by the purchase order line object. When the Purchase Order is matched with a Manual Supplier Invoice, the Used Cost is updated by the voucher created when the invoice is posted. |
When time is reported for a resource of type Person in the Work Task/Time Reports tab. Used/Actual hours is reported by the work task object. When hours is reported for a resource of type Tool/Equipment in the Work Task/Time Reports tab. Used/Actual hours is reported by the work task object. |
|
Request Work Task |
Request work tasks are planned on a Request for service. In the Request Work Task/Material tab, create a requisition line for material, requisition or shipment and specify the quantity required. The supplier price is taken as the planned value. The planned values will be held by the purchase requisition object. The selected supply code determine how the demand is supplied:
In the Request Work Task/Planned Cost and Sales tab, create a line for either cost type External or Expenses and specify the quantity and cost required. The planned values are held by the work task object. |
Planned committed cost is reported for the purchase flow. When the purchase requisition line is added for a Part or No Part, the planned committed cost is reported by the purchase requisition line object. Note: When a Purchase Order is created from the Purchase Requisition, the reporting of planned committed cost is inherited by the purchase order line. When the purchase order line is created for the Part and it is in Planned status, the planned committed cost is reported by the purchase order line object. |
When the Request is released, the associated work task is also updated to released status. The work task object reports committed cost and hours for:
|
When time is reported on the Request Work Task/Time Reports tab for a resource of type Person, Crew or Tool/Equipment, the Used Cost is reported by the work task object. When cost is reported for External and Expenses in the Request Work Task/Planned Cost and Sales tab, the Used Cost is reported by the work task object. Material requisitions: Purchase Orders Receiving Parts: Invoice Matching: When the Purchase Order is matched with a Manual Supplier Invoice, the Used Cost is updated by the voucher created when the invoice is posted. When the Shipment Order is delivered. |
Time is reported in the Request Work Task/Time
Reports tab. When time is reported for a resource of type Person, the Used/Actual hours are reported by the work task object. When hours are reported for a resource of type Tool/Equipment in the, the Used/Actual hours are reported by the work task object. |
|
Planning Item | The value is taken from the Project Deliverables Design /Cost/Hours tab. | When issuing standard planned items from Inventory. | ||||
Customer Order Line | Cost and hours are retrieved from the connected objects, depending on the supply option. Sales Overhead is retrieved from the sales overhead cost calculated for part in Part Cost. | Updated by subsequent supply orders when they are released. Sales Overhead cost is retrieved from Part Cost. | Updated by subsequent supply orders when they are further processed – refer to the relevant object type in this table. | |||
Purchase Requisition Line | Part / No Part | When a PR line is added for a Part/No Part/Rental Part and then released. | ||||
Purchase Order Line | Part/ No Part/ Rental Part | When a PO line is created for the Purchase Part/No Part/Rental Part and is in Planned status. | When the order for a Purchase Part/No Part/Rental Part has been released. | When the order for a Purchase Part/No Part has
been received. When rental events and rental transactions have been generated for the Rental Part. |
When the voucher created upon transfer of transaction has been updated in General Ledger. | |
Purchase Order Change Order | Part / No Part | The delta (in value) between the current purchase order and the active change order (includes statuses Planned, Released, Authorized) for Part/No Part/Rental Part. | When the voucher created upon transfer of transaction has been updated in General Ledger. | |||
Shop Order Requisition | When a shop order requisition line is added for a part through Project Material Requirements Planning (PMRP) or Project Master Scheduling (Project MS) | |||||
Shop Order | When the shop order is in Planned state. Values are taken from the Planned Cost field in the Shop Orders Project Cost Analysis page. |
When the Shop Order is released. Values related
to operations are taken from the routing defined for the shop order
(Shop Order
Operation
page) When the Shop Order is released. Values related to material are taken from the Shop Order components and Shop Order Costing (Shop Order Costs page) When the Shop Order is released. Values related to Subcontracting are taken from the Shop Order routing and Shop Order Costing. When the Shop Order is released. Overhead values will be taken if General Overheads are defined in Part Cost tab. |
Hours are updated when reporting time on the Shop
Order. Updated when reporting time and issuing material to the Shop Order. |
When the voucher created upon transfer of transaction has been updated in General Ledger. | ||
DOP Header | Reported from connected DOP orders (SO, PO) through the DOP Header. | When hours are Reported from connected DOP orders
supply (SO, PO) through the DOP header. Reported from connected DOP order supply (SO, PO) when it is further processed through the DOP Header; refer to the relevant object type in this table. Note! When Transactions have been transferred the used costs are displayed under the voucher rows connections instead of under the DOP header connection. |
Reported from connected DOP orders supply (SO,
PO) when it is further processed all the way to voucher creation upon
transfer of related transactions updated in the General Ledger through
the DOP header. Refer to the relevant object type in this table. Note: When Update GL Vouchers has been run, the actual costs are displayed under the General Ledger Voucher Row connections. |
|||
Material Requisition Line | When the part is Reserved. For parts with Supply Code = Inventory Order. | When the part is Issued. For parts with Supply Code = Inventory Order. | When the voucher created upon transfer of transaction has been updated in General Ledger. | |||
Project Transaction | Time Reporting | When time is reported on an activity. | When the transactions are confirmed and the value in the Create Cost Accounting field of the Report Code is either Yes or No, Update Project Cost. | When the voucher created upon transfer of transaction has been updated in General Ledger. | ||
Cost Reporting | When cost is registered in the Project Time and Cost Registration page. | When the voucher created upon transfer of transaction has been updated in General Ledger. | ||||
Project Inventory Transfer | When the quantity has been transferred from one project inventory to the present project inventory; the original project inventory decreases in cost. | When the voucher created upon transfer of transaction has been updated in General Ledger. | ||||
Sub Contract | Planned cost is reported before activating the revision when selecting the Report Planned Cost slider switch, and is updated when selecting the Update Planned Cost menu option. The planned cost is reported automatically when the revision is activated. | Planned committed cost is reported when call off values are entered on the sub contract. Planned call off amount is equal to the planned committed cost. | Committed cost is reported when the call off is released. | |||
Voucher Row | When voucher rows are created that report cost
to a project activity. Examples:
|
|||||
General Ledger Voucher Row | When vouchers rows that report cost to project activities have been updated to General Ledger. |
Cost and hours will be as follows for different supply options in Customer orders.
Supply Code | Planned | Planned Committed | Committed | Used |
Inventory Order |
Planned cost is retrieved in following hierarchy: 1. Cost set 1 values from IFS Costing. 2. Inventory value of the inventory part. 3. Estimated material cost of the inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported through the connected Customer Order line. |
Updated when subsequent supply orders are released. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery transactions are transferred, used cost is reported under
Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
|
Project Inventory | For manufacturing
parts, cost is retrieved from part costing where as for purchased parts
as in Purchase order Direct (inventory). If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
Updated when subsequent supply orders are released. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery transactions are transferred, used cost from Sales Overhead
is reported under Customer Order to the connected activity.
After transferring transactions, used cost is reported under respective voucher rows. |
|
Purchase Order Direct (inventory) | Planned cost
is retrieved in the following order of priority: 1. Price from Supplier agreement. 2. From price list tab in supplier for purchase part page. 3. Price per part from supplier for purchase part. 4. Cost set 1 values from IFS Costing. 5. Inventory value of the inventory part. 6. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When order is created for the Purchase Part and is in the Planned status.
Cost is reported under Pur Req / Pur Order to the connected activity. |
When order for a Purchase Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery transactions are transferred, used cost is reported under
Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purchase Order Direct 1 (inventory) | Planned cost is retrieved
in the following order of priority: 1. Price from Supplier agreement. 2. From price list tab in supplier for purchase part page. 3. Price per part from supplier for purchase part. 4. Cost set 1 values from IFS Costing. 5. Inventory value of the inventory part. 6. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When order
is created for the Purchase Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a Purchase Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery
transactions are transferred, used cost is reported under Customer
Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purchase Order Direct 2 Alt 3 (inventory) |
Planned cost is retrieved in following hierarchy: 1.Cost set 1 values from IFS Costing. 2. Inventory value of the inventory part. 3. Estimated material cost of inventory part. If a Sales Over Head is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When order is created for the Purchase Part and is in the Planned status.
Cost is reported under Pur Req / Pur Order to the connected activity. |
When order for a Purchase Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery transactions are transferred, used cost is reported under
Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Non-Inventory |
Planed cost is retrieved from Cost field in
Non-Inventory Sales Part page Cost is reported under Customer Order to the connected activity. |
Updated when subsequent supply orders are released. |
Till delivery transactions are transferred, used cost is reported under
Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
|
Project | No planned cost reported. | No planned committed cost reported. | No committed cost reported. | No planned cost reported. |
Purchase Order Direct (non-inv) | Planned cost is retrieved
in the following order of priority: > 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order
is created for the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a No Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till arrival
transactions are transferred, used cost is reported under Customer
Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purchase Order Direct 1 (non-inv) | Planned cost is retrieved
in the following order of priority: 1. Price from Supplier agreement. 2. From price list tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order
is created for the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for the No Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till arrival
transactions are transferred, used cost is reported under Customer Order
to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purchase Order Direct 2 Alt 2 (non-inv) | Planned cost is retrieved
in the following order of priority: > 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order
is created for the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a No Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till delivery
transactions are transferred, used cost is reported under Customer Order
to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Shop Order | Planed cost is retrieved
from Cost set 1 values of IFS Costing. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When the shop order is
in Planned state. Values are taken from the Planned Cost field in the Shop Orders Project Cost Analysis page. |
When the shop order is in released state. | Till delivery transactions
are transferred, used cost from Sales Overhead is reported under
Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. Used Cost incurred in shop order is reported as a typical shop order. |
DOP Order | Planed cost is retrieved
from Cost set 1 values of IFS Costing. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When the DOP order is in released state. | Till delivery transactions
are transferred, used cost from Sales Overhead is reported
under Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. Used Cost incurred in DOP is reported as a typical DOP. |
|
Purchase Order Transit (inventory) | Planned cost
is retrieved in the following order of priority: 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. 4. Cost set 1 values from IFS Costing. 5. Inventory value of the inventory part. 6. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planed cost. Cost is reported under Customer Order to the connected activity. |
When order
is created for the Purchase Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a Purchase Part has been released. Cost for the Purchase Order is
reported under Pur Order to the connected activity.
Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery
transactions are transferred, used cost from Sales Overhead is reported
under Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till arrival transactions are transferred. After transferring, used cost is reported under respective voucher rows. |
IntInt. Purch Order Trans 1 (inventory) | Planned cost
is retrieved in the following order of priority: 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. 4. Cost set 1 values from IFS Costing. 5. Inventory value of the inventory part. 6. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When order
is created for the Purchase Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a Purchase Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery
transactions are transferred, used cost from Sales Overhead is reported
under Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till arrival transactions are transferred. After transferring, used cost is reported under respective voucher rows. |
Int. Purch Order Trans 2 Alt 3(inventory) | Planned cost
is retrieved in following hierarchy: 1. Cost set 1 values from IFS Costing. 2. Inventory value of the inventory part. 3. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
When order
is created for the Purchase Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for the Purchase Part has been released. Cost for the Purchase Order is reported under Pur Req/Pur Order to the connected activity. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
Till delivery
transactions are transferred, used cost from Sales Overhead is reported
under Customer Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. Same as Sales Overhead, used cost from Purchase order is reported under Pur Order to the connected activity till delivery transactions are transferred. After transferring, used cost is reported under respective voucher rows. |
Purchase Order Transit (non-inv) | Planned cost
is retrieved in the following order of priority: 1. Price from Supplier agreement. 2. From price list tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order
is created for the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a No Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till arrival
transactions are transferred, used cost is reported under Pur
Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purch Order Trans 1 (non-inv) | Planned cost is retrieved
in the following order of priority: 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order
is created for the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order
for a No Part has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till arrival
transactions are transferred, used cost is reported under Pur
Order to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Int. Purch Order Trans
2 Alt 2 (non-inv) |
Planned cost is retrieved
in the following order of priority: 1. Price from Supplier agreement. 2. From Price List tab in Supplier for Purchase Part page. 3. Price per part from Supplier for Purchase Part page. Cost is reported under Customer Order to the connected activity. |
When order is created for
the No Part and is in the Planned status. Cost is reported under Pur Req / Pur Order to the connected activity. |
When order for a No Part
has been released. Cost for the Purchase Order is reported under Pur Order to the connected activity. |
Till arrival transactions
are transferred, used cost is reported under Pur Order
to the connected activity. After transferring transactions, used cost is reported under respective voucher rows. |
Not Decided (Inv) |
Planed cost is retrieved in following hierarchy: 1.Cost set 1 values from IFS Costing. 2. Inventory value of the inventory part. 3. Estimated material cost of inventory part. If a Sales Overhead is defined in Part Cost page for the particular part, it is also included in planned cost. Cost is reported under Customer Order to the connected activity. |
Updated when subsequent
supply orders are released. Cost for the Sales Overhead is reported under Customer Order to the connected activity. |
N/A | |
Not Decided (Non-Inv) | Planned
cost is retrieved from Cost field in the Non-Inventory Sales
Part page. Cost is reported under Customer Order to the connected activity. |
Updated when subsequent supply orders are released. | N/A |
Updating of revenue on objects is performed against project revenue elements. Revenue objects do not report progress. The objects report revenue to the activity as follows:
Revenue Object | Estimated | Planned | Preliminary | Posted | Actual |
Activity Estimate | Retrieved from the Estimated Revenue field in the Activity Scope and Schedule/Estimates tab. | ||||
Sales Contract Project
(Sales Contract and Application for Payment) |
Retrieved from Sales Contract Line Items that have the Active revision status. The Report Planned Revenue slider switch can be used to view the previously planned revenue. | ||||
Work Task | When the Work Order Line is transferred to a Customer Order Line. | ||||
Request Work Task | When the Request Line is transferred to a Customer Order Line. | ||||
Customer Order Line Revenue |
When a Customer Order Line or Customer Order Rental Line is connected to an activity. | ||||
Customer Order Invoice Line | When a Customer Order Invoice is created. | ||||
Invoicing Plan | When the Invoicing Plan Line is created with the Sales Amount. | ||||
Project Transaction Revenue | When a Project Transaction is entered which can be invoiced and has a Sales Price. | ||||
Invoice Posting Row
(Project Invoice) |
When the Project/Instant/Customer Invoice is saved. | ||||
External Invoice Posting Row (External Customer Invoice) | When the External Customer Invoice is loaded. | ||||
Voucher Row | When Hold
table voucher rows are created that report revenue to project activities,
for example:
|
||||
General Ledger Voucher Row | When Hold table vouchers rows that report revenue to project activities are updated to General Ledger. |
For this example we work on a project containing only one activity called "Specify and purchase engine for winch". In order to complete this activity some engineers have to do a detailed specification of which engine to buy, and later the purchase department is involved in the communication with the selected supplier. The planned cost driver for all of the objects is Connected Objects, except for the Activity Resources object, for which the planned cost driver is Activity Resources. The progress method is Connected objects.
Step 1
Project Cost Element Estimated Cost Estimated Hours Material 100,000 Work 3,000 30
Sum 103,000 30
Step 2
Now we get the following results:
Project Cost Element Estimated Cost Planned
CostEstimated Hours Planned Hours Material 100,000 Work 3,000 3,200
30
32 Sum 103,000 3,200
30
32
Step 3
Now we get the following results:
Project Cost Element Estimated Cost Planned
CostEarned Value - Cost Scheduled Work - Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours Material 100,000 Work 3,000 3,200
1,600
800
30
32
16
8
Sum 103,000 3,200
1,600
800
30
32 16 8
Step 4
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned Value -
CostScheduled Work -
CostCommitted Cost Estimated Hours Planned Hours Earned Value - Hours Scheduled Work - Hours Material 100,000 90,000 22,500 90,000 Work 3,000 3,200 3,200 800 30 32 32 8 Sum 103,000 93,200 3,200 23,300 90,000 30 32 32 8
Step 5
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned Value -
CostScheduled Work -
CostCommitted Cost Used Cost Actual Cost Material 100,000 90,000 45,000 90,000 Work 3,000 3,200 3,200 1,600 900 Sum 103,000 93,200 3,200 46,600 90,000 900
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
HoursUsed/Actual Hours Material Work 30 32 32 16
10 Sum 30 32 32 16
10
Step 6
Now we get the following results:
Project Cost Element Estimated Cost Planned Cost Earned
Value -
CostScheduled Work -
CostCommitted Cost Used Cost Actual Cost Material 100,000 90,000 45,000 90,000 45,000 45,000 22,500 Work 3,000 3,200 3,200 3,200 2,250 2,250 Sum 103,000 93,200 48,200 93,200 45,000 47,250 24,750
Project Cost Element Estimated Hours Planned Hours Earned Value - Hours Scheduled Work -
HoursCommitted Hours Used/Actual Hours Material Work 30 32 32 32 25 Sum 30 32 32 32 25