Update DOP Structure Dates from Supply

Explanation

This activity is used to update the due dates of DOP orders in a DOP structure to match the latest due dates of their pegged supply orders, provided that at least one pegged supply order exists. As part of this update, the start dates will also be adjusted accordingly.

The due dates of pegged supply orders might change, e.g. due to the usage of constraint based scheduling or manual re-planning. These updated dates often differ from the dates on the DOP orders. In order to avoid getting many alarms due to these differences, this activity makes it possible to update the due date of a DOP order based on the due dates of its pegged supply orders.

To update the due dates of DOP orders in a DOP structure to match the latest due dates of their pegged supply orders, click Update Date/Quantity and then Update Dates from Supply on the DOP Header page.

Prerequisites

This activity requires that at least one DOP order within the structure has at least one pegged supply order.

System Effects

As a result of this activity: