Update DOP Order Date from Supply

Explanation

This activity is used to update the due date of a DOP order to match the latest due date of its pegged supply orders, provided that at least one pegged supply order exists. As part of this update, the start date will also be adjusted accordingly.

The due dates of pegged supply orders might change, e.g. due to the usage of constraint based scheduling or manual re-planning. These updated dates often differ from the dates on the DOP orders. In order to avoid getting many alarms due to these differences, this activity makes it possible to update the due date of a DOP order based on the due dates of its pegged supply orders.

To update the due date of a DOP order with the latest due date of its pegged orders, click Update Dates from Supply and then Order on the DOP Order page or click Update Dates from Supply on the Alarms tab on the DOP Order page.

Prerequisites

System Effects

As a result of this activity