Propagate Date Upstream

Explanation

This activity is used to propagate dates upstream in a DOP structure (to child levels of the structure). The dates at child levels in the DOP structure will be adjusted based on the due date of the DOP order from which the activity is performed.

To propagate dates upstream click Propagate Date/Quantity, then click Propagate Date Upstream on the DOP Order or the DOP Orders page.

Prerequisites

This activity requires that the DOP order has components.

System Effects

As a result of this activity: