Generate Line Schedule
Explanation
Use this function to generate line schedules for a specific part and line.
Line schedules can also be generated via MRP, Master Scheduling, or manually
by entering individual schedule lines. By entering parameters for the schedule
quantities and dates, you can quickly generate a basic line schedule for the
part.
Prerequisites
- A production line with an assigned line calendar must be defined.
- The part
must be defined for the production line before a production schedule can be
created.
- The part must have schedule horizons defined.
- The part must be of one of the following part types: Manufactured,
Manufactured Recipe,
Co-Product or Purchased.
- The structure alternate of the part must not include disassembly
components or co-products as produced parts.
System Effects
As a result of this activity, the system creates a line schedule based on
the parameters you specified.