Assign Technicians to Tasks

Explanation

Line supervisors can assign technicians to a skill requirement as executors, certifiers, or inspectors using the Task Work Assignments page. They can do this using the assignment list, Gantt chart or the Assignments assistant.

The Assignment assistant displays all the unassigned skill requirements for that specific task. The resource list displays all the resources assigned to the same site as of the task who have the certificate for the corresponding Required Skill and Assignment Role

If the outbound flight of the task is canceled or there is no outbound flight, the task can be assigned between the arrival time of the inbound flight and scheduled end time of the work package.

Task work assignments have the following statuses:

Line supervisors cannot assign the inspector role to a user who is already assigned as the executor or certifier within the same skill group.

If configured on the Page Designer page, technicians can also assign other technicians to a skill requirement from the Task Details page.

The supervisor cannot remove assignments that have been started. A supervisor can only remove skill requirements added from the maintenance execution applications.

Prerequisites

  1. Create a site.
  2. Connect calendars and users to the site (Extended Site Info).
  3. Create a resource group (Resource Type: Person).
  4. Connect the site to the resource group.
  5. Add technicians to the resource group (Persons section).
  6. Connect the site and airport using the Airport page.

Note: If the HCM module is used, then the HR schedule of the person's primary scheduling employment is taken to get the availability. If there is no HR Schedule, then the Work Time Calendar directly connected to the person is taken to get the availability. To assign work to technicians, line supervisors should have access to the site. 

System Effects