Use this activity to connect a project activity sequence to a defense contract order delivery- or sub delivery item. All supplies of items listed for a defense contract order, defined with item type CLIN or SLIN, are managed via project and project activities. Once a Project ID is defined in the Project field in the Defense Contract Order section it is possible to connect the project activity sequence with the item, this is the activity which handles the supply. There is a one to one relationship between the defense contract order and a project, but a one to many relationship between the items and a project activity, i.e. the same project activity can be connected to several items.
Connection between the items and a project activity can be done from:
This activity requires that a defense contract order exists in status Active. It also requires that a project in status Active exists holding at least one project activity.
As a result of this activity: